Independent reference. UK figures verified 21 June 2026. No vendor affiliation.
Statutory

Party Wall surveyor cost on a KDR

The Party Wall etc. Act 1996 governs notifiable works to shared walls and deep excavation near neighbours. On a typical KDR with two neighbouring foundations, expect £900-£2,400 per affected neighbour on the agreed-surveyor route, or £2,500-£5,000 per side if a dispute escalates to three-surveyor procedure.

Oliver Wakefield-Smith · Updated 21 June 2026 · Reviewed against Party Wall etc. Act 1996, gov.uk Party Wall guidance, FPWS

When the Act applies

Three triggers[Party Wall Act]: (1) work to a shared (party) wall; (2) excavation within 3m of a neighbouring building going below the neighbour's foundations; (3) excavation within 6m where the cut crosses a 45-degree line from the neighbour's foundation base. New foundations on a KDR almost always trigger (2) or (3) where neighbouring properties are close.

Notice periods

2 months notice for party-wall works; 1 month notice for excavation. The neighbour has 14 days to consent or dissent. Silence is treated as dissent under the Act, so the surveyor process triggers automatically. Issue notices early; the 2-month clock blocks foundation start.

Agreed surveyor vs dissenting

If the neighbour consents and both parties agree to use a single surveyor for the Award, total cost is typically £900-£2,400 per affected neighbour. If the neighbour dissents and appoints their own surveyor, each side instructs their own, costs run £2,500-£5,000 per side, and a third surveyor may be added at the parties' joint cost.

The Party Wall Award

The legal instrument the surveyor(s) produce. Contains: condition schedule (photos of neighbouring property pre-works), permitted hours and methods, indemnity arrangements, schedule of access, and procedure for damage claims. Award is enforceable; breach is a civil matter.

Primary sources

Next decisions